TPM (TOTAL PRODUCTIVE MAINTENANCE) | 8 PILLARS OF TPM

 TOTAL PRODUCTIVE MAINTENANCE (TPM)

  • It is a Japanese Concept which involves all the employees from top to bottom in maintaining and improving the machines and equipment of a particular organization.
  • Its main aim is to keep the machines always working at their best.
  • It improves the performance of machines and reduces operating cost to an organization.
  • It increases Overall Equipment Effectiveness (OEE) i.e. minimum 90% OEE by reducing Downtime, Performance Losses and Quality losses.
  • It was developed by SEIICHI NAKAJIMA during 1950's in Japan.
  • It minimizes the machines failure and breakdown.
  • It helps the teams and departments to exchange their knowledge, skills and experiences.
  • It is the most useful Lean Manufacturing Tool in improving the productivity of an organization.

TOTAL PRODUCTIVE MAINTENANCE IN AN ORGANIZATION

8 PILLARS OF TPM

All Eight Pillars of TPM are mainly focused on preventive techniques for improving machine reliability as stated below:-

Autonomous Maintenance

In this pillar, daily routine maintenance activity such as cleaning of machines, lubrication of all moving parts, tightening of nut & screw and inspection of machine parts are performed by machine operator.

Planned Maintenance

A preventive or schedule maintenance activity which is performed before breakdown occurs in order to avoid unexpected failure of machines in future.

Quality Maintenance

Specifically focused on quality issues and removes source of quality defects by applying root cause analysis.

Focused Improvement

A small group are formed from various departments to identify the cause of machine failure and work together to achieve continuous improvements in machine operation.

Early Equipment Management

Improving the design of new equipment based on knowledge and understanding gained through TPM program.

Education and Training

Educate and train all the employees from time to time about new equipment and basic knowledge of maintenance to achieve TPM goals. 

Administrative and Office TPM

Apply TPM concept to administrative and office functions to remove wasteful activities and supports the plant TPM by improving administrative activities like order processing, procurement of materials, tools & equipment and production scheduling.

Safety, Health and Environmental Conditions

It also aims at zero work accidents, zero pollution and zero burnout which can be achieved by proper maintenance of machines.

Sunday, June 26, 2022

OEE (Overall Equipment Effectiveness) | Calculation of OEE with Example

 OVERALL EQUIPMENT EFFECTIVENESS (OEE)

  • It is a measure of how well a machine is performing as compared to its capacity during scheduled runs.
  • It is a measure of how well a manufacturing operation is running.
  • It measures the effectiveness of manufacturing operation in order to improve the process and increase productivity.
  • It is the calculation made by SEIICHI NAKAJIMA in 1960's in Japan.
  • It helps to identify a problem and losses in manufacturing operations.
  • It is the best practice to improve the performance of machines and manufacturing operations.
  • It is measured in percentage (%).
  • It focuses on continuous improvement process.
  • It is expressed as OEE = A×P×Q , where A → AVAILABILITY, P → PERFORMANCE and Q → QUALITY.
  • If OEE > 85% means the equipment is performing on a WORLD CLASS LEVEL.

Overall Equipment Effectiveness in Manufacturing Operations

CALCULATION OF OEE WITH EXAMPLE


As OEE = AVAILABILITY × PERFORMANCE × QUALITY 

AVAILABILITY = (Available Time − Downtime) ÷ Available Time 

where Available Time = Total Time − Planned Downtime

Planned Downtime = Time Lost in Lunch Breaks, Meetings and any other Regular Scheduled Breaks. 

Downtime = Time Lost in Breakdowns, Repairs, Changeover, Adjustments, Setup etc.

PERFORMANCE = (Running Time − Performance Loss) ÷ Running or Operating Time

OR 

PERFORMANCE = (Standard Cycle Time × Quantity of Product Produced) ÷ Running or Operating Time

where Performance Loss = Time Lost Due to Reduced Speed, Long Cycle Time, Minor Stoppage.

Running Time = Total Time − (Planned Downtime + Downtime)

QUALITY = (Productive Time − Quality Loss Time) ÷ Productive Time 

OR

QUALITY = (Total Quantity Produced − Defective Quantity) ÷ Total Quantity Produced

where Quality Loss Time = Time Lost Due to Quality Issues.

Productive Time = Total Time − (Planned Downtime + Downtime + Performance Loss)

Sunday, June 12, 2022

14 Ways to Boost PRODUCTIVTY in an Organization

 How to Increase Productivity in an Organization

  • By minimizing the wastage of materials.
  • By minimizing or reducing the breakdown of machines.
  • By proper inventory control.
  • By efficient utilization of all the resources like men, machines and materials.
  • By proper design of components.
  • By reducing the downtimes.
  • By using Lean Manufacturing Tools like Kaizen, 5S Methodology, 6 Sigma, PDCA Cycle, Overall Equipment Effectiveness (OEE), Just In Time (JIT), Total Productive Maintenance (TPM).
  • By application of Work Study, Method Study, Time Study and Motion Study.
  • By eliminating the 8 Wastes of Lean.
  • By educating & motivating the employees through proper training sessions from time to time.  
  • By satisfying all the employees/workers.
  • By setting up the daily/weekly/monthly production target.
  • By proper effective communication between employer and employees.
  • By increasing the work time through day and night shifts.
FACTORS WHICH INCREASES PRODUCTIVITY IN AN ORGANIZATION


TQM (Total Quality Management) | Benefits and 8 Principles of TQM

Total Quality Management ( TQM) TQM is a continuous improvement process  which involves all the employees from top to bottom in improving qu...